HTT Rotary
Kiln Pricing (Click on images to enlarge)
The HTT Rotary Kiln
Pyrolizing Furnace components are modular and can be built using the
structural frame of a standard SEALAND type trailer. This will ease
component shipment and installation. The system as quoted will be
equipped with the following components:
1.1
Rotary
screw
feed system (Optional)
1.2 Rotary Kiln Primary Chamber
1.3 Secondary Afterburner
1.4 Burners - Natural gas
1.5 Control System
PRICE: Design, Fabrication, FOB Shops,
Technical
Assistance, installation assistance, startup, training of operating
personnel. Freight is not included in price.
Typical
System
Designs:
Rotary Kiln w/Afterburner
| HTT |
lbs./hr |
R
-
(Diameter/Length) |
| HTT 500R-48/240-G |
500 #/hr |
6 TPD |
| HTT 1000R-72/240-G |
1,000 #/hr |
12 TPD |
| HTT 2000R-96/360-G |
2,000 #/hr |
25 TPD |
Dual Rotary Kiln w/Afterburner
| HTT |
lbs./hr |
R
-
(Diameter/Length) |
| HTT 4000R2-96/360-G |
4,000 #/hr |
50 TPD |
| HTT 8000R4-96/360-G |
8,000 #/hr |
100 TPD |
Options
| HTT |
R
-
(Diameter/Length) |
| HTT Screw type
Feeder System |
6-100 TPD |
Note: Processing rates may be
different than that of solid waste rates. The optional scrubbers and
charging systems must be sized based on the application. The chambers
are fabricated and shipped by common carrier.
TERMS: 35% with order, 35% when fabrication
period
is 50% completed, 30% after customers inspection prior to shipment and
delivery. Overseas projects will require an irrevocable letter of
credit and 100% payment prior to shipment.
Delivery: Allow 2 weeks for approval
drawings.
Equipment will be ready for shipment 8-10 weeks after the receipt of
valid purchase order, progress payments, and all required approvals.
Installation: HTT will assist during
customer’s
installation and startup no additional charge. Not included are travel
and living expenses.
Warranty: HTT Guarantees that the unit will
be
free of defects in materials and workmanship for one (1) year from the
time of delivery. Components purchased by HTT for use in making a
complete package will be limited to the warrantee offered by those
specific manufacturers. HTT shall assist in the applications for
permits as required.
Excluded Items: HTT shall supply only the
items
described above. Additional items required are to be supplied by the
customer. Such items may consist of the screw feeder, emission testing,
building, modifications to support pad, electrical feeds, tipping
floor, boiler feed system, ash container, overhead crane capability,
etc.
|