HTT Rotary Kiln Pricing
The HTT Rotary Kiln Pyrolizing Furnace components are modular and can be built using the structural frame of a standard SEALAND type trailer. This will ease component shipment and installation. The system as quoted will be equipped with the following components:
1.1 Rotary screw feed system (Optional)
1.2 Rotary Kiln Primary Chamber
1.3 Secondary Afterburner
1.4 Burners - Natural gas
1.5 Control System
PRICE: Design, Fabrication, FOB Shops, Technical Assistance, installation assistance, startup, training of operating personnel. Freight is not included in price.
Typical System Designs:
Rotary Kiln w/Afterburner
| HTT | lbs./hr | R - (Diameter/Length) | | HTT 500R-48/240-G | 500 #/hr | 6 TPD | | HTT 1000R-72/240-G | 1,000 #/hr | 12 TPD | | HTT 2000R-96/360-G | 2,000 #/hr | 25 TPD |
Dual Rotary Kiln w/Afterburner
| HTT | lbs./hr | R - (Diameter/Length) | | HTT 4000R2-96/360-G | 4,000 #/hr | 50 TPD | | HTT 8000R4-96/360-G | 8,000 #/hr | 100 TPD |
Options
| HTT | R - (Diameter/Length) | | HTT Screw type Feeder System | 6-100 TPD |
Note: Processing rates may be different than that of solid waste rates. The optional scrubbers and charging systems must be sized based on the application. The chambers are fabricated and shipped by common carrier.
TERMS: 35% with order, 35% when fabrication period is 50% completed, 30% after customers inspection prior to shipment and delivery. Overseas projects will require an irrevocable letter of credit and 100% payment prior to shipment.
Delivery: Allow 2 weeks for approval drawings. Equipment will be ready for shipment 8-10 weeks after the receipt of valid purchase order, progress payments, and all required approvals.
Installation: HTT will assist during customer’s installation and startup no additional charge. Not included are travel and living expenses.
Warranty: HTT Guarantees that the unit will be free of defects in materials and workmanship for one (1) year from the time of delivery. Components purchased by HTT for use in making a complete package will be limited to the warrantee offered by those specific manufacturers. HTT shall assist in the applications for permits as required.
Excluded Items: HTT shall supply only the items described above. Additional items required are to be supplied by the customer. Such items may consist of the screw feeder, emission testing, building, modifications to support pad, electrical feeds, tipping floor, boiler feed system, ash container, overhead crane capability, etc. |